Action
|
Results of Successful Performance |
Initiating |
| 1. Demonstrate project need and feasibility. |
 | A document confirming that there is a need for the project deliverables
and describing, in broad terms: the deliverables, means of creating the deliverables,
costs of creating and implementing the deliverables, benefits to be obtained by
implementing the deliverables. |
|
| 2. Obtain project authorization. |
 | A "go/no go" decision is made by the sponsor. |
 | A project manager is assigned. |
 | A "project charter" is created which:
 | Formally recognizes the project |
 | Is issued by a manager external to the project and at a high enough
organizational level so that he or she can meet project needs |
 | Authorizes the project manager to apply resources to project activities |
|
|
| 3. Obtain authorization for the phase. |
 | A "go/no go" decision is made by the sponsor which
authorizes the project manager to apply organizational resources to the activities of a
particular phase |
 | Written approval of the phase is created which
 | Formally recognizes the existence of the phase |
 | Is issued by a manager external to the project and at a high enough
organizational level so that he or she can meet project needs |
|
|
Planning |
| 4. Describe project scope. |
 | Statement of project scope |
 | Scope management plan |
 | Work breakdown structure |
|
| 5. Define and sequence project activities. |
 | An activity list (list of all activities that will be performed on the
project) |
 | Updates to the work breakdown structure (WBS) |
 | A project network diagram |
|
| 6. Estimate durations for activities and resources
required. |
 | Estimate of durations (time required) for each activity and assumptions
related to each estimate |
 | Statement of resource requirements |
 | Updates to activity list |
|
| 7. Develop a project schedule. |
 | Project schedule in the form of Gantt charts, network diagrams, milestone
charts, or text tables |
 | Supporting details, such as resource usage over time, cash flow
projections, order/delivery schedules, etc. |
|
| 8. Estimate costs. |
 | Cost estimates for completing each activity |
 | Supporting detail, including assumptions and constraints |
 | Cost management plan describing how cost variances will be handled |
|
| 9. Build a budget and spending plan. |
 | A cost baseline or time-phased budget for measuring/monitoring costs |
 | A spending plan, telling how much will be spent on what resources at what
time |
|
| 10. Create a formal quality plan. (optional) |
 | Quality management plan, including operational definitions |
 | Quality verification checklists |
|
| 11. Create a formal project communications plan. (optional)
|
 | A communication management plan, including:
 | Collection structure |
 | Distribution structure |
 | Description of information to be disseminated |
 | Schedules listing when information will be produced |
 | A method for updating the communications plan |
|
|
| 12. Organize and acquire staff. |
 | Role and responsibility assignments |
 | Staffing plan |
 | Organizational chart with detail as appropriate |
 | Project staff |
 | Project team directory |
|
| 13. Identify risks and plan to respond. (optional) |
 | A document describing potential risks, including their sources, symptoms,
and ways to address them |
|
| 14. Plan for and acquire outside resources. (optional)
|
 | Procurement management plan describing how contractors will be obtained |
 | Statement of work (SOW) or statement of requirements (SOR) describing the
item (product or service) to be procured |
 | Bid documents, such as RFP (request for proposal), IFB (invitation for
bid),etc. |
 | Evaluation criteria -- means of scoring contractor's proposals |
 | Contract with one or more suppliers of goods or services |
|
| 15. Organize the project plan. |
 | A comprehensive project plan that pulls together all the outputs of the
preceding project planning activities |
|
| 16. Close out the project planning phase. |
 | A project plan that has been approved, in writing, by the sponsor A
"green light" or okay to begin work on the project |
|
| 17. Revisit the project plan and replan if needed. |
 | Confidence that the detailed plans to execute a particular phase are
still accurate and will effectively achieve results as planned. |
|
Executing |
| 18. Execute project activities. |
 | Work results (deliverables) are created. |
 | Change requests (i.e., based on expanded or contracted project) are
identified. |
 | Periodic progress reports are created. |
 | Team performance is assessed, guided, and improved if needed. |
 | Bids/proposals for deliverables are solicited, contractors (suppliers)
are chosen, and contracts are established. |
 | Contracts are administered to achieve desired work results. |
|
Controlling |
| 19. Control project activities. |
 | Decision to accept inspected deliverables |
 | Corrective actions such as rework of deliverables, adjustments to work
process, etc. |
 | Updates to project plan and scope |
 | List of lessons learned |
 | Improved quality |
 | Completed evaluation checklists (if applicable) |
|
Closing |
| 20. Close out project activities. |
 | Formal acceptance, documented in writing, that the sponsor has accepted
the product of this phase or activity. |
 | Formal acceptance of contractor work products and updates to the
contractor's files. |
 | Updated project records prepared for archiving. |
 | A plan for follow-up and/or hand-off of work products |
|