Earned Value Analysis

- an aid in defining the status of a project.

by Sean McEvoy, Chief Information Officer of ETP

EVA is an acronym for Earned Value Analysis. It is a method of using the value of the work already completed on the project to indicate what will be the actual schedule and cost figures at the completion of the project.

EVA is a general term for the formal Cost/Schedule Status Reporting (C/SSR) requirements originally defined by the US Department of Defence. All US Government Departments now insist upon C/SSR when commissioning projects and private organisations are beginning to insist that their external contractors do likewise.

The primary measurements used in C/SSR are:

Budgeted Cost of Work Scheduled (BCWS): the value of the original planned work.
Budgeted Cost of Work Performed (BCWP): the value of the completed work. This is the Earned Value.
Actual cost of Work Performed (ACWP): the actual cost of the completed work.

Following from these 3 primary measurements we can examine a number of useful indicators:

Schedule variance (SV): (BCWP - BCWS) A negative value indicates the project is over budget or behind schedule, or both!
Schedule Variance Percent (SV%): (BCWP.100/BCWS) The variance from BCWP, as a percentage, between what has actually been earned. by now what should have been earned.
Cost Variance (CV): (BCWP - ACWP) A negative value indicates being over budget.
Cost Variance Percent (CV%): (BCWP.100/ACWP) The variance from BCWP, as a percentage, between what has actually been earned by now and what it has cost.

Using these base measurements plus the variances we can calculate some completion figures.

Budget at completion (BAC): This is the final value of the BCWS, the figure we expect the project to cost if all goes according to plan.
Estimated cost at completion (EAC): This is the BAC minus the-current CV. In other words, the cost of the project' in the unlikely event of the remainder of the project going exactly according to plan.
Calculated cost at completion (CAC): This is the BAC divided by the current CV%. In other words, the cost of the project if the remainder of the project goes the same way as the project to date.

Using events on an actual programming project as an example, we will use EVA to help us monitor the status'
The table below gives the planned figures for work and cost for a 12 month project. (The cost figures are calculated from the daily rates of the programmers but all figures have been rounded and simplified for clarity). For simplicity, BCWS can be considered as the planned cumulative cost (Fig.1)

Plan

End Jan

End Feb

End Mar

End Apr

End May

End June

Monthly Work

50

100

150

150

150

150

Cumul. Work

50

150

300

450

600

750

             
Monthly Cost

500

1000

1500

1500

1500

1500

BCWS

500

1500

3000

4500

6000

7500

             
 

End July

End Aug

End Sept

End Oct

End Nov

End Dec

Monthly Work

150

150

150

150

100

50

Cumul. Work

900

1050

1200

1350

1450

1500

             
Monthly Cost

1500

1500

1500

1500

1000

500

BCWS

9000

10050

12000

13500

14500

15000

(Fig 1)

Having planned the project, we can now execute it. At the end of each month we input the actual work figures for the programmers and the % complete figures for each task. These figures directly give us the ACWP and the BCWP. The remaining Earned Value fields are then calculated and these give the 'project manager a month to month indication of the status of the project.

The following is a summary of what happened in the project each month for the first 6 months and the spreadsheet below gives the Earned Value figures resulting from this.

January
Actual work (ACWP=300) less than planned (i.e. ACWP < BCWS)
Schedule is slow but EV is fine (i.e. SV% < 100 but CV% = 100 because BCWP = ACWP)
This situation has arisen because we were slow at assigning people to the project.

February
Work exactly as planned.
Schedule still slow, EV still fine.
At this point we will allocate some extra work at weekends to try an recoup some of the lost schedule.

March
Work for month greater than planned.
Schedule doesn't come in much as some problems were encountered. At this point we are both over budget and behind schedule. We will continue the extra working.

April
Work greater than planned.
Schedule has now come back on plan.
We will revert to normal working.

May
Work slightly more than planned (some tasks were underestimated).
Schedule fine.

June
Work to plan.
Schedule to plan.
A most unusual month!

Actual

End Jan

End Feb

End Mar

End APR

End May

End June

Monthly Cost

500

1000

1500

1500

1500

1500

BCWS

500

1500

3000

4500

6000

7500

             
BCWP(EV)

300

1000

1600

1600

1500

1500

ACWP

300

1000

1800

1800

1600

1500

             
Cumul. EV

300

1300

2900

4500

6000

7500

Cumul. ACWP

300

1300

3100

4900

6500

8000

CV

0

0

200

-400

-500

-500

SV

200

200

-100

0

0

0

CV%

100%

100%

93.6%

91.8%

92.3%

93.7%

SV%

60%

87%

96.7%

100%

100%

100%

BAC

15000

15000

15000

15000

15000

15000

EAC

15000

15000

15200

15600

16100

16600

CAC

15000

15000

16034

16333

16250

16000

Fig 2

The situation at the end of the 6 month period is that our project is back on schedule but at an increased cost. Note the changing values of EAC and CAC as we go through from January to June.

 

Contacto:

Renato Lopes
DHV
FBO - Consultores, S.A.
Dept. Project Management
Tel. 214 127 400
Fax. 214 127 490
E-mail. renato.lopes@fbo.pt
Rua Dr. António Loureiro Borges, 5 - 6º
Arquiparque
Miraflores
1495-131 Algés - Portugal

renatolopes.50megs.com
Email : rll@clix.pt
Tel. 934 408 347